Cadence Minerals completes hot commissioning at Amapá iron ore processing plant in Brazil

5 Nov 2026 16:35 reported by Joy Liu

A A A
Cadence Minerals plc announced that operator DEV Mineração S.A. finished 30-day hot commissioning at the Azteca processing facility in Amapá, Brazil. The plant processed around 6,200 wet tons of iron ore feed and produced 2,800 wet tons of concentrate, reflecting a 45% mass recovery rate over 160 operating hours at a 40-ton-per-hour feed rate.

DEV submitted compliance reports to the Amapá State Environmental Secretariat on October 29 to complete the Operating Licence application. The plant used accessible lower-grade feed to expedite licensing.

Cadence maintains an annual production target of about 380,000 tons of 65% iron concentrate, aiming for first commercial shipments before the end of 2026, pending regulatory approval.

Back to Steel News

Related News

LME nickel futures rebound to $16,201 per ton on strong macro data

  • Raw Materials
  • 12 Nov 2026 16:43

Kazakhstan extends 6-month metal scrap export ban

  • Raw Materials
  • 12 Nov 2026 16:42

Ferrexpo temporarily halts Ukrainian iron ore output due to power grid disruptions

  • Raw Materials
  • 12 Nov 2026 16:42

SGS & Carbonix partner to test P180 direct reduction technology for HBI production

  • Raw Materials
  • 12 Nov 2026 14:39

Simandou targets 120 million tons of iron ore by end-2027 despite logistics bottlenecks

  • Raw Materials
  • 12 Nov 2026 14:33

Metal Price Index

Learn more

LME Official Bid Price

  • Zinc
  • 3,760.00
  • 3,720.00
  • Aluminum
  • 3,155.00
  • 3,030.00
  • Copper
  • 13,711.00
  • 13,650.00
  • Nickel
  • 16,000.00
  • 16,190.00

Learn more